Fresh off days of record rainfall and flooding, the Bunnell City Commission spent much of its Monday, Nov. 23, 2026, meeting dealing with storm damage, debating whether to create a new stormwater fee, and backing a plan to clean up the city’s finances. The meeting began at 7 p.m.
A storm that overwhelmed the city
Staff told the board the city received 12.9 inches of rain since Nov. 16, sending about 1.43 billion gallons of water through a stormwater system that serves roughly 4,100 acres. The wastewater treatment plant, at 79% capacity on Nov. 16, climbed to as high as 168% in the days after. The city declared a local state of emergency (Proclamation 2026-18) effective 7 a.m. Nov. 19 for seven days, which lets it track expenses for possible federal reimbursement and waive some procedures. Officials cautioned that no reimbursement has been approved.
The storm also disrupted trash service. When the Waste Management transfer station flooded and closed Nov. 19, the city had to haul collected trash to the Putnam landfill — a trip of more than an hour each way through standing water — to avoid canceling pickups. Staff said the budget impact would mainly be higher overtime and fuel costs.
Staff shared photos of flooding across town, including a nearly submerged fire hydrant on U.S. 1 South, flooding on Highway 100 West, and two road closures: Old Moody Boulevard (where a vehicle went into a ditch) and East Woodland Street.
East Woodland Street repair approved
The most detailed debate came over East Woodland Street, where the roadway collapsed after a long-troubled drainage culvert was undermined. Staff laid out three options: a temporary fix for $29,000 to $59,000, a permanent fix with proper concrete headwalls for $105,000 to $120,000, or a permanent road closure. Staff recommended the permanent fix, warning that a temporary one would mean “throwing money away” because “eventually, it will come back to this.”
Commissioners agreed the fix could not wait, with several noting the danger. “We were lucky nobody got hurt,” one said, pointing out a driver could have hit the hole “in the dead of the night.” After adding the item to the agenda, the board voted to approve a permanent fix, naming Four C’s as the low bidder at $105,000. Contractor Chelsea Herbert said the precast headwalls would take about six weeks to manufacture, putting the job at roughly three months, though crews would work on site for only about a week. Vice Mayor Rogers asked her to sharpen her pencil for a possible 10% discount, and she agreed to see what she could do.
Members debated how to pay for it. The city has about $1.3 million in reserves, but Commissioner Young said he opposed tapping them if possible: “Reserves are reserved for a reason.” The approved motion directs staff to confirm the city followed proper bidding rules, explore emergency grant funding, and process a budget amendment to cover the cost.
A push for a stormwater fee
Commissioner Seacrest used the flooding to renew a call for a stormwater fee, saying the city has long discussed one but never acted. He asked staff to bring a code amendment to the December meeting that would give the city the legal ability to set such a fee later by resolution. “If last week was an example of our lack of preparedness … if that doesn’t motivate us into some kind of action, forget it,” he said. Staff clarified that passing the ordinance would not create a fee, only allow one, with any actual fee decided after a workshop with business owners and the public in the new year.
The idea drew pushback during public comment. Property owner Steve Wooden, whose flood-prone house is on piers, warned that a stormwater fee would be the start of a “slippery slope” of added fees and said residents made clear with Amendment 3 that they want lower costs. “You don’t fix this problem by finding new revenue. You fix this problem by fixing your spending,” he said, adding, “reserves are meant for a rainy day. Hello, it’s rain.”
Several residents tied the flooding to growth. Allison Nobles said the photos proved what residents warned about when the city approved large developments: “If we’re already flooding now, as we are removing the trees, we’re increasing the water.” Chelsea Herbert, who lives on Old Haw Creek Road, said that despite the flooding, the downstream drainage “is working” because water receded within two days. Garrett Holland noted the region’s water drains slowly through Black Branch, Haw Creek, and Crescent Lake, and backs up when rivers are high: “It’s been that way my whole life … and it will continue to do it.”
Consent, land use, and routine business
The board approved its consent agenda, including generator maintenance, sewer inspection, and street-sweeping contracts. On second reading, it approved land-use and rezoning changes for about 14.92 acres on State Road 100 West (recently annexed into the city) to commercial medium and B1 business zoning, and a change of 0.92 acres from industrial to single-family medium density for applicant Andrew Howard, who scaled back plans because of environmental constraints.
The commission also approved a wastewater treatment facility plan tied to a $13.1 million federal grant (through Hurricane Milton recovery) that staff said is “free to the city,” and a final budget amendment for the year. In old business, after an earlier tie, the board appointed Whitney Andrews to the Planning, Zoning, and Appeals Board over Gerard Holland. For its 2027 legislative priorities, the city kept its focus on the Coquina Hall building and local roads, and added stormwater funding to the list.
A new finance and audit plan
In his report, Interim City Manager David Brannon laid out concerns about the city’s finances and a plan to fix them. He said city auditors “have flagged the same bookkeeping problem three years in a row,” that a reported $835,000 budget mistake was noted last year, and that a late financial report cost the city $13,527 in half-cent sales tax revenue. He also said the former city manager extended the audit contract with James Moore just before leaving — a deal signed Oct. 2, after the manager had submitted his resignation — raising the cost by 20% to 37% and totaling about $242,200 over four years, without coming to the commission for a vote or the mayor’s signature.
Brannon asked the board to direct the city attorney to send a certified letter to James Moore about the extension, to keep the 2026 audit on schedule, to form an Auditor Selection Committee under state law, and to seek a separate independent review of the city’s cash handling, procurement, grants, utility billing, payroll, and internal controls, reporting findings publicly. The board approved his recommendations and named Commissioner Atkinson chair of the Auditor Selection Committee. The city attorney said the city may be able to void the improperly signed contract but would need to investigate. Brannon also announced Finance Director Christy Moss will retire Dec. 18.
Vice Mayor Rogers asked that purchasing (P) cards be pulled from all but directors, citing reports of misuse in other cities and within Bunnell. Staff confirmed some employees had used P-cards “without getting authorization from their supervisor,” and the board reached consensus to limit the cards. Resident Allison Nobles said her news feed is “inundated” with public-records requests over P-card spending in Daytona Beach and urged Bunnell to “get ahead of this,” supporting an external audit.
Economic development and the road ahead
Brannon said early estimates show Amendment 3 could cost Bunnell about $600,000 to $700,000 a year in property tax revenue, and pitched a plan to attract business to fill the gap. Citing a rural economic development summit, he said companies “rule out most towns online before they ever call,” and proposed putting the city’s site information online, visiting existing businesses, rebuilding trust with the state, and hiring a marketing contractor capped at $100,000 a year. “Who’s selling Bunnell?” he recalled hearing at a recent town hall.
He also described options for the coming budget squeeze, including asking departments to look at 15% reductions and using state Department of Corrections work teams at no cost for jobs like stormwater work. Vice Mayor Rogers called for budget workshops after the new year to “separate the needs from the wants.”
Reports and thanks
The city clerk announced the 14th annual Christmas in Bunnell for Dec. 11 at J.B. King Park, and the board agreed to keep its Dec. 28 meeting at 7 p.m. with a light agenda. The police chief reported the city’s Thanksgiving “Baskets of Love,” funded by staff donations, served 36 families, about 144 people. Staff also noted new flooding damage at the Coquina building’s kitchen addition, which may force a temporary closure.
Commissioners closed with praise for city staff’s storm response and for Brannon’s early work. “I couldn’t imagine somebody stepping into that position and immediately improving it tenfold,” Commissioner Seacrest said. Vice Mayor Rogers added, “Don’t wear out doing good. Keep doing good … just do your job and tell the truth.” The meeting then adjourned.
Note: Several names are spelled phonetically from the meeting audio