Bunnell City Commission Unanimously Denies Project Butterfly Landfill Following Nearly 11-Hour Hearing

BUNNELL, Fla. — After months of growing controversy, public opposition, and concerns about the potential environmental and economic impacts on western Flagler County, the Bunnell City Commission voted unanimously Wednesday, October 28, to deny a special exception application for Project Butterfly, a proposed 610-acre landfill along County Road 45.

The 5-0 decision followed a nearly 11-hour hearing that brought together residents, farmers, attorneys, environmental experts, elected officials, and representatives of the proposed development. What began as a special meeting at 9 a.m. continued into the evening as commissioners heard extensive testimony and reviewed the circumstances surrounding the project’s initial approval.

For residents who had spent weeks organizing, researching the proposal, and expressing concerns about its potential impact on the surrounding community, the decision marked a significant turning point in the debate over the future of the property.

The proposed Class I landfill, submitted by Cocomero LLC, would have introduced a major waste disposal operation into an area characterized largely by agricultural activity, rural properties, and environmentally sensitive lands.

Although the applicant maintained that the project could operate within applicable regulations and environmental safeguards, opponents questioned whether a landfill of that size belonged in an area where farming and agricultural operations have long been established.

Ultimately, commissioners determined that the application did not meet the requirements necessary to receive the requested special exception.

A Controversial Proposal From the Beginning

Project Butterfly became a source of controversy almost immediately after details of the proposal became public.

The development had been handled under a Florida economic development confidentiality provision, which allowed certain information about the project to remain undisclosed during the early stages of consideration.

Details were released on August 31, just one day before the Bunnell Planning, Zoning and Appeals Board was scheduled to consider the application.

The limited time between the public disclosure and the hearing became a major point of criticism among residents and officials who argued that the community had not been given a reasonable opportunity to evaluate the proposal or understand its potential consequences.

On September 1, the Planning, Zoning and Appeals Board voted 3-1 to approve the special exception, subject to 21 conditions.

That approval did not end the controversy.

Instead, it prompted 18 appeals challenging the decision, including appeals involving Flagler County and neighboring property owners.

Residents continued to raise questions about the project’s compatibility with existing land uses, its potential effects on groundwater and agricultural production, and whether the initial review process had adequately addressed the concerns of those living and working nearby.

The appeals ultimately brought the matter before the Bunnell City Commission for Wednesday’s lengthy hearing.

Nearly 11 Hours of Testimony and Deliberation

Wednesday’s meeting was conducted as a de novo hearing, meaning commissioners were tasked with considering the application and evidence independently rather than simply determining whether the planning board had followed the proper procedures.

The format allowed the commission to examine the proposed landfill, hear testimony, and determine whether the application satisfied the city’s requirements for a special exception.

Throughout the day, commissioners heard from representatives of the applicant, attorneys, experts, farmers, surrounding property owners, and other interested parties.

The hearing included discussion of the project’s proposed operations, environmental protections, surrounding land uses, traffic concerns, and potential effects on existing agricultural businesses.

Questions about the compatibility of the landfill with Bunnell’s comprehensive plan and zoning regulations became central to the proceedings.

Supporters of the application argued that the project was eligible for consideration under the city’s special exception process and that additional regulatory oversight would be required before the landfill could begin operating.

Opponents maintained that the proposed use presented conflicts with the surrounding agricultural community that could not be adequately resolved through conditions or future permitting requirements.

After hours of testimony and discussion, the commission moved toward a decision.

Commissioners voted to grant the appeals considered during the proceedings, reversing the earlier planning board approval, and subsequently voted unanimously to deny the special exception application.

Agricultural Community Raises Serious Concerns

One of the most significant issues throughout the Project Butterfly debate was the potential impact on western Flagler County’s agricultural community.

The area surrounding the proposed landfill includes working farms and properties used for agricultural production, making compatibility with existing operations a major consideration.

Farmers and neighboring property owners expressed concerns about how a large-scale landfill could affect their ability to continue operating successfully.

Among the issues raised were groundwater contamination, stormwater runoff, odors, dust, increased truck traffic, and the possibility of negative perceptions surrounding agricultural products grown near a landfill.

For farmers, the concerns extended beyond environmental questions.

Testimony during the hearing addressed the potential financial consequences of locating a landfill near established agricultural operations.

One agricultural business reportedly faced the possibility of losing buyers concerned about purchasing produce grown near a landfill, even if contamination had not occurred.

Such concerns raised questions about whether the project could create economic consequences for neighboring farms simply because of its proximity.

The possibility of lost customers, reduced demand, or uncertainty surrounding agricultural products became part of the broader discussion about the landfill’s compatibility with existing businesses.

Commissioners were asked to consider not only whether the proposed facility could meet environmental regulations but also whether its presence could interfere with agricultural operations that were already established in the area.

Groundwater and Environmental Protection Become Major Issues

Environmental concerns were another central focus of the hearing.

Residents and neighboring property owners questioned how the proposed landfill could affect groundwater resources, nearby agricultural land, wildlife, and surrounding environmentally sensitive areas.

Because groundwater plays an important role in agricultural operations and the broader environment, potential contamination was among the issues repeatedly raised during the debate.

Concerns also included how stormwater would be managed, whether surrounding properties could experience runoff-related impacts, and what protections would be in place to prevent problems over the long term.

The applicant’s representatives maintained that environmental safeguards and additional permitting requirements would apply to the proposed facility.

A Class I landfill in Florida is subject to state environmental regulations, including requirements intended to address waste containment, groundwater monitoring, and operational safety.

However, the existence of a state permitting process did not resolve the separate question before Bunnell commissioners: whether the proposed land use satisfied the city’s local approval requirements.

The commission was responsible for evaluating the special exception under applicable city regulations and land-use policies.

The hearing highlighted the distinction between whether a landfill might eventually satisfy environmental permitting standards and whether the proposed location was appropriate under Bunnell’s planning requirements.

Questions Surrounding Traffic and Infrastructure

The potential effect of the landfill on surrounding roads was also part of the discussion.

A large waste disposal facility would introduce additional commercial vehicle activity into the area, raising questions about traffic volumes, road conditions, safety, and the ability of existing infrastructure to accommodate landfill-related operations.

Residents expressed concerns about the possibility of increased truck traffic along rural roads used by local motorists, agricultural vehicles, and nearby property owners.

The discussion also raised questions about whether the information provided was sufficient to evaluate the full extent of potential traffic impacts.

For residents accustomed to the area’s rural character, the prospect of increased heavy truck activity represented another possible change associated with the proposed development.

Traffic considerations were among several issues commissioners weighed when evaluating whether the application satisfied the requirements for approval.

Bunnell’s Comprehensive Plan Plays a Central Role

As the hearing progressed, the city’s comprehensive plan emerged as a key factor in the commission’s decision.

A comprehensive plan establishes a municipality’s long-term policies for land use, development, infrastructure, environmental protection, and the preservation of existing community characteristics.

In Bunnell, those policies include provisions addressing agricultural land and the relationship between existing farming operations and proposed nonagricultural development.

Vice Mayor John Rogers ultimately made the motion to deny the special exception, citing concerns related to the city’s comprehensive plan and the protection of existing agricultural uses.

His reasoning focused on the potential conflicts between the proposed landfill and surrounding agricultural operations, including questions involving water quality, air quality, crop safety, wildlife, conservation lands, and economic impacts.

The city’s planning policies concerning conflicts between agricultural and nonagricultural land uses became particularly important to the discussion.

The commission considered whether introducing a landfill into the area would be consistent with policies intended to protect existing agricultural activities.

Commissioner Atkinson seconded the motion to deny the application.

All five commissioners voted in favor, resulting in a unanimous rejection of the proposed special exception.

Flagler County Officials Also Challenged the Proposal

Opposition to Project Butterfly was not limited to nearby residents and property owners.

Flagler County was among those challenging the earlier planning board decision, bringing additional attention to the potential implications of the proposal beyond Bunnell’s municipal boundaries.

Flagler County Commissioner Andy Dance raised questions about whether the proposed landfill was an appropriate use under the property’s Agriculture and Silviculture zoning designation.

The issue was particularly significant because the proposal involved a facility that would serve a substantially different purpose from the agricultural activities already taking place in the surrounding area.

Although the property falls within Bunnell’s jurisdiction, the potential effects of the landfill were a concern for residents and officials throughout Flagler County.

The project raised broader questions about land-use compatibility, regional infrastructure, environmental protections, and the relationship between municipal development decisions and neighboring county properties.

The county’s involvement underscored the regional significance of the proposed development and the concerns surrounding its potential impact.

Applicant Defends the Proposed Landfill

Throughout the approval process, representatives of Cocomero LLC maintained that the proposed landfill was eligible for consideration under Bunnell’s land-use regulations.

The applicant’s position centered on the special exception process, which allows certain uses to be considered when specified conditions and approval criteria are met.

Representatives argued that the project could be developed with appropriate safeguards and that additional state permitting requirements would provide oversight of environmental and operational concerns.

The proposed development also included measures intended to address its relationship with surrounding properties, including buffer areas.

According to reporting from Spectrum News 13, discussion surrounding the project included a proposed 600-foot buffer and an alternative presented by the applicant.

However, commissioners were not required to approve the special exception simply because the project would face additional environmental review.

Their responsibility was to determine whether the application met the city’s requirements and was compatible with applicable land-use policies.

The commission’s unanimous denial reflected its conclusion that the necessary approval criteria had not been satisfied.

Community Participation Shapes the Debate

Beyond the technical and legal arguments, the Project Butterfly controversy generated significant public interest throughout Flagler County.

Residents attended meetings, followed developments in the application process, and raised questions about the long-term consequences of allowing a landfill in western Flagler County.

For some, the issue centered on protecting agricultural operations and the livelihoods connected to them.

Others focused on groundwater protection, wildlife, rural road safety, and the potential effect on surrounding property owners.

The controversy also brought attention to the process through which major development proposals are reviewed and how much information residents should receive before decisions are made.

The initial confidentiality surrounding Project Butterfly, followed by the short period between public disclosure and the planning board’s approval, became a recurring concern.

Wednesday’s hearing provided an opportunity for the commission to examine the application in greater detail and hear from parties who challenged the earlier decision.

The nearly 11-hour proceeding demonstrated the complexity of the issues involved and the amount of information commissioners were asked to consider.

Mayor Catherine Robinson acknowledged those who participated in the lengthy hearing and thanked attendees for the respectful manner in which they presented their concerns.

What Does the Decision Mean for Project Butterfly?

The unanimous vote means that Project Butterfly did not receive the special exception necessary to move forward under the application considered by the City Commission.

The decision also reverses the earlier approval granted by the Planning, Zoning and Appeals Board.

However, the denial does not necessarily mean the proposal can never return.

The applicant may have options to challenge the commission’s decision through the legal process, depending on applicable procedures and deadlines.

Any such challenge would involve a separate process from Wednesday’s hearing.

For now, the city’s decision leaves the proposed landfill without the local special exception approval it sought.

The outcome also illustrates the role comprehensive plans, zoning regulations, and public hearings can play when municipalities consider development proposals that could significantly change the character or use of surrounding land.

A Significant Decision for Western Flagler County

The debate over Project Butterfly brought attention to competing considerations involving waste disposal infrastructure, economic development, agricultural preservation, environmental protection, and local land-use authority.

For the applicant, the proposal represented a potential landfill development subject to local approval and additional regulatory oversight.

For neighboring farmers and residents, it raised concerns about changes that could affect their properties, businesses, and surrounding environment for years to come.

Wednesday’s decision resolved the special exception application before the City Commission, but the broader discussion about land use and the future of western Flagler County may continue.

The commission’s unanimous vote placed the city’s comprehensive plan and its protections for existing agricultural uses at the center of the decision.

After nearly 11 hours of testimony, questions, and deliberation, all five Bunnell commissioners reached the same conclusion: Project Butterfly would not receive the requested special exception.

For now, the proposed 610-acre landfill remains denied, with any future developments dependent on whether the applicant chooses to pursue additional legal or administrative action.

The post Bunnell City Commission Unanimously Denies Project Butterfly Landfill Following Nearly 11-Hour Hearing first appeared on Flagler County Buzz.